Liz Dupre of Clear Water Environmental submitted plans dated 7/1/24, and is requesting four local upgrades: 1. Septic tank 6' from foundation (10' required) 2. Septic tank 8' from property line (10' required) 3. SAS 10' from foundation (20' required) 4. Use one deep hole in proposed disposal area
Stephen Olson, president of H2Olson Engineering, Inc is requesting a variance request from the Board, to alow a permanent portable toilet at Aquarion's water treatment plant located at 579 Main St